Jubilee Park Upgrades

Share on Facebook Share on Twitter Share on Linkedin Email this link

Update: April 28, 2023

During the Regular Meeting of Council held on April 24, Council gave its approval for the procurement and implementation of rubber surfacing for the phase three playground area. Funding of $120,000 for the rubber flooring will come from the Growing Communities Fund. Ground construction will begin in early spring with the rubber surfacing and playground installation completed by late summer or early fall.


Update: March 22, 2023

At the March 20, 2023 Regular Meeting of Council, Council passed a motion to award the contract for Jubilee Park playground equipment to Swing Time Distributors Ltd. Council has

Update: April 28, 2023

During the Regular Meeting of Council held on April 24, Council gave its approval for the procurement and implementation of rubber surfacing for the phase three playground area. Funding of $120,000 for the rubber flooring will come from the Growing Communities Fund. Ground construction will begin in early spring with the rubber surfacing and playground installation completed by late summer or early fall.


Update: March 22, 2023

At the March 20, 2023 Regular Meeting of Council, Council passed a motion to award the contract for Jubilee Park playground equipment to Swing Time Distributors Ltd. Council has requested staff present cost options for rubber surfacing to consider at a future Council meeting. Final construction is still expected to be completed by fall of 2023.


Update: February 2, 2023

At the January 30, 2023 Regular Meeting of Council, the results of the public engagement survey for the next phase of Jubilee Park was presented to Council and Council passed a motion to endorse the playground equipment procurement plan. Of the 187 who participated in the survey, 118 (63.1%) chose Option 2. The project team will now contact the three vendors who initially submitted to this project to provide bids for the final project based on the preferred design.

Once the successful proponent is awarded the contract, we plan on beginning with the ground preparation, with the final construction expected to be complete by fall of 2023.



Update: December 21, 2022

Thank you to everyone who participated in the survey for the next phase of Jubilee Park! Our project team is reviewing your feedback, and we will report back in January. Your input is appreciated, and we look forward to bringing some exciting new additions to Jubilee Park in 2023!



Have your say in the future of Jubilee Park! This is your community park, and we would like your input. The Jubilee Park Playground first opened in 2016, and the District of North Saanich continues to make enhancements and add new features. Jubilee Park Playground has become a popular destination for many kids and families, and for adults who use it as a starting point for runs or a gathering place for workouts.

Earlier this year, Council approved $250,000 towards the final phase of upgrades. We have worked within this budget to present concepts that include options that are inclusive and diverse, promoting a multi-faceted, sensory-rich play space for all.

Which of the following two options would you like to see added to the playground at Jubilee Park? Please vote through the survey below until Thursday, December 15, 2022.

Staff will rely on your feedback to make final decisions about the composition of the new equipment in Jubilee Park. If you have additional comments, please email the project team at: jubilee@northsaanich.ca




Page last updated: 17 May 2023, 12:14 PM